Why 80% of delays are not lost due to execution

Introduction: The myth of the “failing construction site”

In the collective imagination of the construction industry, a delayed project is often synonymous with poor site execution:

  • lack of productivity
  • Poor organisation
  • Ineffective teams

 

Yet, the reality of complex projects (EPC, nuclear, infrastructure) is quite different:

The majority of delays are not “lost”... they are misidentified, poorly structured or poorly defended.

The real problem: understanding ≠ proving

A project can be delayed for dozens of reasons:

  • late modifications
  • Poorly managed interfaces
  • Customer decisions
  • External constraints

But within a contractual framework, that is not enough.

 

For a delay to legally “exist”, it must be demonstrated:

  • the cause
  • Responsibility
  • the impact on the schedule

 

This is precisely the role of the Delay analysis :

Identify, quantify and assign delays with a structured methodology

 

Without this, the delay is invisible... even if it is real.

 

2. All delays are not equal

This is a major error on the projects.

A delay is only valuable if it impacts the critical path.

Simple example:

  • Delay on a non-critical activity no contractual impact
  • delay on the critical path Extension of time + potential cost

 

In practice:

  • There are many delays.
  • few are contractually valid

 

Delays are classified (critical, excusable, compensable, etc.), and each type has different consequences for claims.

Key conclusion:

80%: some delays are “unaccountable” because they are incorrectly scheduled.

 

3. The decisive factor: documentation

This is where it all comes down to it.

An undocumented delay is a non-existent delay.

Projects produce massive data:

  • emails
  • Reports
  • Radio Frequency Interference
  • amended plans
  • site diaries

 

But without structure:

 impossible to:

  • rebuild the timeline
  • To prove causality
  • demonstrate the impact

Or

solid documentation allows for the identification of events, quantification of their impact, and attribution of responsibilities

 

4. Delays are rarely an execution problem

It's counter-intuitive but fundamental.

In major projects:

  • The teams are performing correctly overall
  • schedules are drifting due to systemic factors

 

The common real causes:

  • late client decisions
  • Insufficient design maturity
  • Vague contractual interfaces
  • poorly integrated changes
  • Poor float management

 

And above all:

Delays become a problem when they are not structured into the schedule.

 

5. The real issue: turning time into a contractual lever

A well-analysed delay allows:

  • one Extension of Time (EOT)
  • one penalty protection
  • one Financial claim (extension, disruption, etc.)

 

The expert's role is clear:

To analyse events, assign responsibilities and quantify the impact to enable financial valuation.

 

6. Why 80% delays are “lost”

Because the projects:

❌ Do not structure their schedule
do not follow the critical path
❌ do not document correctly
❌ don't think “contractual”
Do not anticipate claims

 

Result:

  • Delays exist
  • but they are not neither proven nor defensible

 

7. ALVID positioning (high value)

That's exactly where the difference lies between:

❌ A classic planner

who follows progress

A strategic approach (ALVID)

→ which turns the schedule into a contractual asset

 

Conclusion — Time is a contractual capital

Projects do not waste time.
They are losing the ability to prove it.

 

The real gap is not operational.
It is analytical, contractual and strategic.

Do you have any more questions?

Our Latest Publications