Why 80% of delays are not lost due to execution
Introduction: The myth of the “failing construction site”
In the collective imagination of the construction industry, a delayed project is often synonymous with poor site execution:
- lack of productivity
- Poor organisation
- Ineffective teams
Yet, the reality of complex projects (EPC, nuclear, infrastructure) is quite different:
The majority of delays are not “lost”... they are misidentified, poorly structured or poorly defended.
The real problem: understanding ≠ proving
A project can be delayed for dozens of reasons:
- late modifications
- Poorly managed interfaces
- Customer decisions
- External constraints
But within a contractual framework, that is not enough.
For a delay to legally “exist”, it must be demonstrated:
- the cause
- Responsibility
- the impact on the schedule
This is precisely the role of the Delay analysis :
Identify, quantify and assign delays with a structured methodology
Without this, the delay is invisible... even if it is real.
2. All delays are not equal
This is a major error on the projects.
A delay is only valuable if it impacts the critical path.
Simple example:
- Delay on a non-critical activity no contractual impact
- delay on the critical path Extension of time + potential cost
In practice:
- There are many delays.
- few are contractually valid
Delays are classified (critical, excusable, compensable, etc.), and each type has different consequences for claims.
Key conclusion:
80%: some delays are “unaccountable” because they are incorrectly scheduled.
3. The decisive factor: documentation
This is where it all comes down to it.
An undocumented delay is a non-existent delay.
Projects produce massive data:
- emails
- Reports
- Radio Frequency Interference
- amended plans
- site diaries
But without structure:
impossible to:
- rebuild the timeline
- To prove causality
- demonstrate the impact
Or
solid documentation allows for the identification of events, quantification of their impact, and attribution of responsibilities
4. Delays are rarely an execution problem
It's counter-intuitive but fundamental.
In major projects:
- The teams are performing correctly overall
- schedules are drifting due to systemic factors
The common real causes:
- late client decisions
- Insufficient design maturity
- Vague contractual interfaces
- poorly integrated changes
- Poor float management
And above all:
Delays become a problem when they are not structured into the schedule.
5. The real issue: turning time into a contractual lever
A well-analysed delay allows:
- one Extension of Time (EOT)
- one penalty protection
- one Financial claim (extension, disruption, etc.)
The expert's role is clear:
To analyse events, assign responsibilities and quantify the impact to enable financial valuation.
6. Why 80% delays are “lost”
Because the projects:
❌ Do not structure their schedule
do not follow the critical path
❌ do not document correctly
❌ don't think “contractual”
Do not anticipate claims
Result:
- Delays exist
- but they are not neither proven nor defensible
7. ALVID positioning (high value)
That's exactly where the difference lies between:
❌ A classic planner
who follows progress
A strategic approach (ALVID)
→ which turns the schedule into a contractual asset
Conclusion — Time is a contractual capital
Projects do not waste time.
They are losing the ability to prove it.
The real gap is not operational.
It is analytical, contractual and strategic.