Pourquoi 90% des plannings ne tiennent pas contractuellement
Introduction :
In the large projects industry - particularly in an EPC environment - scheduling is ubiquitous.
It structures execution, aligns teams, drives performance.
And yet.
When a project goes off track, deadlines are missed, and responsibilities need to be established…
the vast majority of plans become unenforceable contractually.
Not because they are technically false.
But because they were never designed to be defended.
Pourquoi 90% des plannings ne tiennent pas contractuellement
In the large projects industry - particularly in an EPC environment - scheduling is ubiquitous.
It structures execution, aligns teams, drives performance.
And yet.
When a project goes off track, deadlines are missed, and responsibilities need to be established…
the vast majority of plans become unenforceable contractually.
Not because they are technically false.
But because they were never designed to be defended.
1. The fundamental misunderstanding: piloting vs proving
An operational plan is designed to:
to organise the work
coordinate the interfaces
optimise the sequences
A contractual schedule, on the other hand, must allow for:
demonstrate a credible critical path
to establish a causal link between an event and an impact
justify an extension of time (EOT) entitlement
withstand a contrary analysis
However, in the majority of projects, this distinction is never made.
The programme is nevertheless a key contractual requirement, particularly in FIDIC contracts (Clause 8.3).
But in practice, it is treated as a mere management tool.
Direct consequence:
The day the schedule has to serve as proof... it fails.
2. A network logic that is often indefensible
A contractually robust schedule relies on impeccable network logic.
In practice, it is regularly observed:
activities with no predecessors or successors (open ends)
excessive use of “hard” constraints to force deadlines
unexplained lag
unstable or artificial critical paths
These defects are sometimes tolerated during the execution phase.
They become prohibitive during the claims phase.
Why?
Because all delay analysis rests on a key assumption:
The critical path must be credible and demonstrable.
If logic is contestable, then:
The impact of delays is questionable
The responsibility is questionable
The claim collapses
3. The absence of a clear contractual baseline
Another major weakness lies in the management of baselines.
Too often
the versions are not formally approved
The developments are not tracked
several “references” coexist without a clear hierarchy
Or, any analysis of delay begins with a simple question:
What is the enforceable contractual baseline?
Without a clear answer:
no deviation can be reliably measured
no blame can be attributed
No claim can be soundly constructed.
In other words, without a robust baseline,
The schedule loses its legal value.
4. A disconnect between planning and contract
In many projects, the schedule is drawn up independently of the contract.
It reflects:
a technical logic
production constraints
organisational choices
But it doesn't always translate:
contractual milestones
sequence obligations
the conditions for access to or submission of works
extension mechanisms
This disconnection is critical.
Because in a dispute situation, it is not technical logic that prevails,
but The contractual interpretation of time.
A schedule not aligned with the contract cannot support a legal position.
5. An untraceable and unenforceable advance
Progress tracking is often the most fragile point.
We frequently observe:
subjective percentages
non-uniform measurement rules
post-hoc corrections
a lack of traceability for updates
During a dispute, these practices are immediately attacked.
The question then becomes:
On what objective basis was this advancement measured?
If the answer is not clear and documented:
the data is rejected
The analysis is discredited.
The contractual position is weakened
6. A lack of knowledge of reference standards
Delay analysis cannot be improvised.
It is based on recognised reference frameworks such as:
The SCL Delay and Disruption Protocol
AACE International Recommended Practice 29R-03
These standards define:
analysis methods (TIA, Windows, As-Planned vs As-Built...)
terms of use
the limitations and biases of each approach
Without mastery of these frameworks:
The chosen methodology is questionable
The conclusions are fragile
The expert's credibility is being called into question
7. Inadequate management of competitive delays
In complex projects, several delays often coexist:
Client delays
contractor delays
batch interference
External constraints
The concept of concurrency is then central.
Yet, it is rarely treated correctly:
Lack of fine-grained temporal analysis
Confusion between excusable and inexcusable delays
Lack of clear responsibilities
Or, without this analysis:
No allocation of responsibility is possible
no right to compensation can be robustly established
8. A lack of narrative and justification
Ultimately, a timetable alone is never enough.
To be defensible, it must be accompanied by:
Methodological notes
explicit hypotheses
justified choices
documented analyses
Without this narration:
The schedule remains a technical representation.
With her:
it becomes one Structured and defensible argument.
Conclusion — Time as a Contractual Asset
A planning document is not contractually binding when it cannot:
demonstrate a clear link between cause and effect
withstand a contrary analysis
to be independently audited
In complex EPC environments,
Time is not just a steering variable.
It's a Contractual employee.
And like any asset, it must be structured, secured and defended.
Strategic positioning
Organisations that perform well are not those that produce the most plans.
These are the ones that produce schedules:
legally actionable
methodologically robust
strategically aligned with their contractual interests
It is precisely in this gap that value is created.
ALVID Consulting
Clarity in Complexity — Turning schedules into contractual evidence.