"A bad reference schedule? That's what international standards say."

PMBOK, PRINCE2, AACE, DCMA, SCL... All the major reference systems agree: "A poorly designed reference schedule can jeopardize an entire project."

In project management, the reference planning (or Baseline planning) is supposed to represent the formal commitment to deadlines. But when it is poorly structured, unrealistic or obsolete, it becomes a major risk factor.

However, in the real world, we still see too many baselines:

  • poorly sequenced,
  • unrealistic,
  • not validated,
  • or never updated.

 

The result? Unanticipated drift, unclear decisions, and sometimes... lost claims.

What the standards say:

 

🔷 PMBOK (PMI) - The baseline is the measuring instrument

«The reference schedule is used to measure deviations. Without initial reliability, there's no steering.»

✅ It must be :

  • Realistic
  • Collaborative
  • Based on documented assumptions
  • Formally validated

 

🔷 PRINCE2 - The plan is a living product

«A schedule is not a static document, it's an evolving guide to the project.»

A fixed or theoretical plan quickly becomes an illusion. It must be :

  • Updated at every stage of the project
  • Connected to operational reality

 

🔷 DCMA 14-Point Assessment - Technical planning control

«A reference schedule must meet strict criteria to be credible.»

Examples:

  • < 5% of activities without logic
  • No abuse of constraints or lags
  • Consistent margins
  • Clear critical path

If not? ➡️ Planning considered invalid.

 

🔷 AACE (RP 29R-03 & 37R-06) - Basis for a serious delay analysis

«Without valid planning, no delay analysis can be considered reliable.»

✅ Recommendations:

  • Logically and contractually consistent planning
  • Version traceability
  • Full documentation of assumptions

 

🔷 SCL Protocol (Delay & Disruption) - The baseline, the key to any claim

«An unrealistic or broken baseline invalidates the legitimacy of a claim.»

 

 In litigation, weak planning is weak evidence. SCL recommends :

  • Logically linked, validated and updated schedules
  • Formally rebaselined baselines
  • A rigorous version archive

 

In plain English:

Poor reference planning means :

  • A loss of control
  • Downgraded anticipation
  • A fragile legal framework

 

And this, even if the rest of the project is well managed.

 

Best practices (common to all standards) :

  • Co-construct the schedule with the business players
  • Formally validate with project management
  • Update regularly (and track baselines)
  • Document all changes
  • Ensure technical quality (logic, constraints, margins, etc.)

 

What about you?

Have you ever had to deal with a poorly structured reference schedule? How did you rectify the situation? What standards or practices do you follow?

 

More questions?

Our latest articles